SunTrust Oil and its JV Partner have completed the drilling and completion of Umu 18 on the Western culmination of the Umusadege field to a total depth (TD) of 9,583ft and cored from9,253ft – 9,314ft MD (61ft). Umu 18 was completed as a dual string multi-zone producer with Sand XIV on the Short String while Sands XVIa and Sand XXa were completed on the Longs String.
We plan to commence the initial Well clean-up on October 4th, 2019 once we displace Well to diesel and Rig down to clear space for the clean-up operation.